[1]United States Court of Appeals for the Federal Circuit
01-1630
Donald H. Rumsfeld, SECRETARY OF DEFENSE,
Appellant,
v.
APPLIED COMPANIES, INC.,
Appellee.
David B. Stinson, Trial Attorney, Commercial Litigation Branch, Civil Division, Department of Justice, of Washington, DC, argued for appellant. With him on the brief were Robert D. McCallum, Jr., Assistant Attorney General; David M. Cohen, Director; and Deborah A. Bynum, Assistant Director. Of counsel on the brief was Donald Tracy, Trial Attorney, Defense Supply Center, Richmond, Defense Logistics Agency, of Richmond, Virginia.
Peter B. Jones, Jones & Donovan, of Newport Beach, California, argued for appellee.
Appealed from: Armed Services Board of Contract Appeals
United States Court of Appeals for the Federal Circuit
01-1630
Donald h. rumsfeld,
SECRETARY OF DEFENSE,
Appellant,
v.
APPLIED COMPANIES, INC.,
Appellee.
__________________________
DECIDED: December 10, 2002
__________________________
Before SCHALL, DYK, and PROST, Circuit Judges.
Opinion for the Court filed by Circuit Judge SCHALL. Opinion concurring-in-part and dissenting-in-part filed by Circuit Judge DYK.
SCHALL, Circuit Judge.
This suit arises from a requirements contract between the Defense Logistics Agency (ÒDLAÓ), a component of the Department of Defense, and Applied Companies, Inc. (ÒAppliedÓ). Under the contract, among other things, DLA was to purchase from Applied all of its requirements for two types of refrigerant storage cylinders during the period from June of 1994 through June of 1995, with an option year. In its request for proposals (ÒRFPÓ), DLA estimated its annual requirements for the two types of cylinders at 62,945 and 56,550 units, respectively. Prior to contract award, DLA determined that the estimates in the RFP were greatly overstated. However, this information was not communicated to any of the offerors, including Applied. Applied was awarded the contract, but after ordering only approximately 10% of the estimated quantity of cylinders, DLA terminated the contract for convenience on February 6, 1995.
Following the denial of its termination for convenience settlement proposal and a claim for breach of contract, Applied appealed to the Armed Services Board of Contract Appeals (ÒBoardÓ) under the provisions of the Contract Disputes Act, 41 U.S.C. ¤¤ 601‑613 (ÒCDAÓ). Ruling on cross-motions for summary judgment, the Board concluded that DLA had breached the requirements contract by negligently failing to inform Applied that the estimates of its cylinder requirements in the RFP were inaccurate. Determination of the amount of damages was reserved for further proceedings. Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-1 B.C.A. (CCH) ¦ 31,325 (Feb. 26, 2001) (ÒApplied IÓ). DLAÕs subsequent motion for reconsideration was denied. Applied Cos., Inc., ASBCA Nos. 50,749, 50,896, and 51,662, 01-2 B.C.A. (CCH) ¦ 31,430 (May 21, 2001) (ÒApplied IIÓ). The Secretary of Defense (ÒgovernmentÓ) now appeals the BoardÕs decision. Because the Board did not err in holding that DLA had breached its contract with Applied, we affirm.
BACKGROUND
I.
The pertinent facts, which are not in dispute, are set forth in Applied I. They are as follows:
The requirements contract stemmed from a procurement for cylinders to store R-12 and R-114 refrigerants, which are classified as ÒClass I Ozone Depleting Substances,Ó or ÒODSs.Ó Applied I, 01-1 B.C.A. at 154,730. DLA, which was charged with building and maintaining a stockpile of ODSs for the Department of Defense, assessed the existing inventories of ODSs, the amount of ODSs likely to be used and recycled, and the amount of ODSs needed to ensure availability for mission critical uses. In June of 1993, based on its assessment, DLA developed estimates of the amount of R-12 and R-114 refrigerants that it needed to acquire and, by extension, the number of cylinders that would be required to store those refrigerants. Id. On July 14, 1993, DLA issued the RFP for the requirements contract. DLA estimated in the RFP that 62,945 cylinders would be needed for the storage of R-12 refrigerants and that 56,550 cylinders would be needed for the storage of R-114 refrigerants, for a total of approximately 120,000 cylinders during the one year term of the contract.[2] Id. The RFP stated that the variation in actual quantity purchased would be Òplus 03% minus 03%.Ó The estimated quantities were the same for the option year. Id. On or about August 11, 1993, Applied, among others, responded to the RFP. Applied was the lowest responsive offeror.
In January of 1994, after initiating a pre-award survey, DLA determined that the reserve requirements for R-12 and R-114 refrigerants were considerably lower than previously believed. Id. at 154,731. As a result, DLA established that the number of R-12 and R-114 storage cylinders that would be needed during the upcoming year were 2,555 and 1,037, respectively. Id.
On June 20, 1994, DLA awarded the requirements contract to Applied, accepting its bid of $52.60 per cylinder. Id. In the notice of award, DLA repeated the estimates contained in the RFP. Under the contract, for the period June 20, 1994, to June 14, 1995, DLA was obligated to Òorder from the contractor all the [cylinders] that are required to be purchased by the Government.Ó The contract also provided that the Òquantities of [cylinders] specified in the schedule are estimates only and are not purchased by this contract.Ó The contract incorporated various clauses from the Federal Acquisition Regulations (ÒFARÓ).
CONCLUSION
For the foregoing reasons, the decision of the Board holding that DLA breached its requirements contract with Applied is affirmed. In the next phase of the case, consistent with this opinion, the Board will determine the amount of the recovery, if any, to which Applied is entitled by reason of DLAÕs breach.[7]
COSTS
No costs.
AFFIRMED.
United States Court of Appeals for the Federal Circuit
01-1630
Donald H. Rumsfeld, SECRETARY OF DEFENSE,
Appellant,
v.
APPLIED COMPANIES, INC.,
DYK, Circuit Judge, concurring in part and dissenting in part
In the present contract the government undertook two relevant obligations: (1) to purchase its actual requirements from the plaintiff and (2) to accurately estimate its requirements. There was no breach of the first obligation, but the majority holds that the second obligation was breached because the government, either in bad faith or negligently, provided an incorrect estimate. I am in full agreement with the majority so far. Having found that the second obligation was breached, however, the majority unaccountably denies the plaintiffÕs claim for lost profits for the admitted breach. The measure of damages the majority uses is unsupported by our precedent and contrary to the general law of contracts. Moreover, it leaves the contractor largely uncompensated for the breach and provides almost no incentive for the government to avoid such breaches in the future. I respectfully dissent.
The majority cites no case in which there was a bad faith or negligent misrepresentation in a requirements contract but lost profits were denied. In Everett Plywood & Door Corp. v. United States, 419 F.2d 425 (Ct. Cl. 1969), Crown Laundry & Dry Cleaners, Inc. v. United States, 29 Fed. Cl. 506 (Fed. Cl. 1993), Cactus Press/Power Enterprises, Inc., GPOBCA 20-99 (Bd. Contract App. Jan. 31, 2001), and HKH Capitol Hotel Corp., ASBCA No. 47,575, 98-1 B.C.A. (CCH) ¦ 29,548, at 146,467 (Jan. 26, 1998), cited by the majority as support for denying lost profits, ante at 20-22, the plaintiffs did not seek lost profits for a governmental misrepresentation. Thus, those opinionsÕ silence as to the possibility of lost profits recovery for misrepresentation is completely without significance.
In Everett Plywood the plaintiff contracted with the Forest Service to purchase timber on a parcel of government land for a price that would decrease over time, so that the plaintiff would pay less per unit for the timber the more timber it cut and purchased. 419 F.2d at 427. The government negligently misrepresented how much timber was on the parcel so that the plaintiffÕs average cost per unit was higher than it had contemplated. Id. at 429. The plaintiff sought a price adjustment, and our predecessor court awarded the difference between the per unit price the contractor had to pay for the timber it cut and the effective price per unit it would have paid for the timber if the contractor had been able to cut the quantity estimated by the Forest Service. Id. at 433. There is no indication that the plaintiff sought lost profits, and the opinion does not discuss or even mention a lost profits issue.
In none of the other cited cases involving negligent misrepresentation did the contractor seek lost profits. In Crown Laundry, the contractor sought only equitable adjustment of the contract, and the parties stipulated the actual dollar amount of damages at the outset were the contractor to prevail. 29 Fed. Cl. at 514. Likewise, in Cactus Press, the contractor sought only equitable adjustment of the contract price. The same is true of HKH Capitol Hotel Corp. 98-1 B.C.A. ¦ 29,548 at 146,471. The equitable adjustment sought by the contractors in those cases appears to have consisted mainly of increased costs associated with the unexpected volume. But in Crown Laundry the amount of damages was not disputed, and in neither Cactus Press nor HKH Capitol Hotel Corp did the Board find that the contractor was entitled to an equitable adjustment.[8] Those cases therefore did not reach the question of what measure should be used. The statements in each case that equitable adjustment of the contract price was available to the contractor (if it could establish that it was harmed by a negligently prepared bid) simply restated the claim asserted by the contractor. Those statements were not addressed to lost profits and have no bearing on lost profit recovery.[9]
Without a controlling precedent, this court Òappl[ies] ordinary principles of contract construction and breach.Ó United States v. Winstar Corp., 518 U.S. 839, 871 (1996) (plurality opinion); accord Lynch v. United States, 292 U.S. 571, 579 (1934) (Òrights and dutiesÓ of government contract Òare governed generally by the law applicable to contracts between private individuals.Ó). The majority must recognize that there is no controlling precedent in this area, as it observes that Ò[n]o case has been cited to us in which, under a requirements contract, a contractor was allowed to recover anticipatory profits as damages for a breach of contract resulting from negligently prepared estimates,Ó ante at 19, and then it cites no case in which, in that situation, lost profits have been denied. Accordingly, we must look to the general law of contracts.
As the majority recognizes, the rule in this area is that lost profits are available to the non-breaching party, assuming foreseeability. As we have said,
ÒOne way the law makes the non-breaching party whole is to give him the benefits he expected to receive had the breach not occurred.Ó Glendale Federal Bank FSB v. United States, 239 F.3d 1374, 1380 (Fed. Cir. 2001) (citing Restatement (Second) of Contracts ¤ 344(a)(1981)). A partyÕs expectation interest is the Òinterest in having the benefit of his bargain by being put in as good a position as he would have been in had the contract been performed.Ó Restatement (Second) of Contracts ¤ 344(a)(1981). Expectation damages are recoverable provided they are actually foreseen or reasonably foreseeable, are caused by the breach of the promisor, and are proved with reasonable certainty.
Bluebonnet Sav. Bank, F.S.B. v. United States, 266 F.3d 1348, 1355 (Fed. Cir. 2001) (emphasis added). The leading authorities on contract agree that the normal measure of damages includes lost profits. As it was put in the First Restatement of Contracts, Òcompensatory damages will be given for the net amount of the losses caused and gains prevented, in excess of savings made possible.Ó Restatement (First) of Contracts ¤ 329 cmt. a (1932). See also Arthur Linton Corbin, Corbin on Contracts ¤ 992 (Interim ed. 2002) (quoting First Restatement with approval); Restatement (Second) of Contracts ¤ 347 (1981).
To determine how to calculate the gains prevented by Defense Logistics AgencyÕs (ÒDLAÓ) breach, we should look to breach of warranty cases. If DLA had warranted to Applied Companies, Inc. (ÒApplied) that the requirements contract would provide 120,000 cylindersÕ worth of work, damages would be awarded to compensate the contractor for the benefit of the expected bargain, not for the value of the contract as it was without the misrepresentation. For example, the Uniform Commercial Code provides, ÒThe measure of damages for breach off warranty is the difference . . . between the value of the goods accepted and the value they would have had if they had been as warranted.Ó UCC ¤ 2-714(2) (1989). This is in keeping with the rule that Ò[o]rdinarily, the damages recoverable for a breach of contract are measured on the basis of the value of the promised performance.Ó Corbin, supra, ¤ 1030 (emphasis added).
To be sure, in this case there was, in effect, only a warranty that the requirements were properly estimated; the quantity ordered could have been higher or lower. But such uncertainty, contrary to the majorityÕs assertion, does not bar recovery. Although we have not specifically addressed the lost profits issue, we have repeatedly recognized that when the government allows bidding on either requirements or indefinite quantities contracts, it is reasonable and foreseeable for contractors to rely on government estimates. Medart, Inc. v. Austin, 967 F.2d 579, 581 (Fed. Cir. 1992) (Ò[P]resumably contractors rely on the [governmentÕs] proffered estimates in formulating their bids, so the government must act in good faith and use reasonable care in computing its estimated needsÓ); Clearwater Forest Indus., Inc. v. United States, 650 F.2d 233, 239 (Ct. Cl. 1981) (Ò[A] prospective purchaser should reasonably be expected to base his operating plans and cost estimates on [government estimates]Ó); Womack v. United States, 389 F.2d 793, 801 (Ct. Cl. 1968) (ÒAssuming that the bidder acts reasonably, he is entitled to rely on Government estimates as representing honest and informed conclusions.Ó). Indeed, it is the very purpose of quantity estimates to induce such reliance; otherwise, as our predecessor court said, the estimate would be Òsurplussage at best or deception at worst.Ó Womack, 389 F.2d at 801.
Where such reliance is reasonable, Ò[i]f a reasonable probability of damage can be clearly established, uncertainty as to the amount will not preclude recovery.Ó Ace-Federal Reporters, Inc. v. Barram, 226 F.3d 1329, 1333 (Fed. Cir. 2000) (quoting Locke v. United States, 283 F.2d 521, 524 (Ct. Cl. 1960)). In circumstances in which the breach destroyed all value and made recovery under the contract impossible, courts have measured the value of the contract right at the time of the breach. Corbin, supra, ¤ 1030; E. Allen Farnsworth, Farnsworth on Contracts ¤ 12.15 (2d ed. 1998). So too, at the time the government made the contract with Applied, it was worth something definite, of which the governmentÕs estimate was highly probative. Alternatively, recovery could be based on other evidence of the contract value -- how Applied valued the contract when it was signed, for example, or how other, similarly situated companies valued requirements contracts. See Farnsworth, supra, ¤ 12.15. Taking into account expected variations from the estimate, the Board should award lost profits based on the amount of likely purchases given the estimate. It is particularly inappropriate for the majority to foreclose lost profit damages at this stage, before Applied has even had the opportunity to present evidence on the matter.
The majority holds that an award of lost profits would overcompensate Applied because, had the government disclosed its actual requirements, Applied would have either Òsubmitted a bidÓ on the contract as it was or Òdeclined to bid on the contract and thus made no profit at all.Ó Ante at 19. In short, the majority contends, it would have been impossible for Applied to recover the profits on this contract, because even absent the breach, Applied Òwould not have expected to sell, and it would not have sold, 120,000 cylinders.Ó Ante at 18. But that characterization removes the misrepresentation from the measure of damages, as if it had never happened. The famous Bristol Seed case, treated by Corbin, provides an illustration of the majorityÕs approach. Corbin, supra, ¤ 1026 (describing White v. Miller, 71 N.Y. 118 (N.Y. 1877)). In that case, the buyer purchased seed from a seller who warranted that it was fit for human consumption. It was in fact mixed seed only good for animal feed. The buyer was due damages based on the difference between the value of the seed as warranted and the value of the actual seed, including lost profits. Id. Under the majorityÕs theory of damages, however, the buyer could not recover expected profits because there would not have been any; the seed was unfit for human consumption.
Here the contractor assumed the risk that the governmentÕs requirements would actually be less than the estimate; the contractor did not assume the risk that the governmentÕs requirements estimate would be deliberately or negligently misstated. The majorityÕs measure of damages thus effectively erases the breach. Far from Òconvert[ing] the contract . . . to one in which DLA guaranteed Applied a certain level of business,Ó as the majority asserts, ante at 19, awarding lost profits merely reflects the general measure of damages.
The consequence of todayÕs decision is that the government may misrepresent its requirements with impunity so long as the contractor suffers no increase in costs. That seems to me to be bad policy as well as bad law. I respectfully dissent.
[2] The RFP and contract involved other sizes and models of cylinders that are not at issue in this dispute. In the interest of clarity, we hereafter refer to the two types of cylinders at issue as the ÒcylindersÓ covered by the contract.
[3] The Board denied AppliedÕs claim for anticipatory profits for the option year that DLA did not exercise. The Board also denied the governmentÕs motion for summary judgment dismissing AppliedÕs appeal of DLAÕs unilateral determination of the termination for convenience settlement. Applied I, 01-1 B.C.A. at 154,734. Since the termination settlement claim and the breach of contract claim sought the same lost profits, the Board sustained both appeals Òwith the understanding that one of the appeals will be dismissed during the quantum phase after an agreement is reached or a determination is made as to the date when interest begins.Ó Id. at 154,735.
[4] We have exclusive jurisdiction "of an appeal from a final decision of an agency board of contract appeals pursuant to section 8(g)(1) of the Contract Disputes Act of 1978." 28 U.S.C. ¤ 1295(a)(10) (emphasis added). The CDA provides that all claims must first be submitted to the contracting officer for a decision. See 41 U.S.C. ¤ 605(a); Dewey Elecs. Corp. v. United States, 803 F.2d 650, 654 (Fed. Cir. 1986). After receiving an adverse decision from the contracting officer, the contractor may appeal that decision to the appropriate agency board of contract appeals. See 41 U.S.C. ¤ 607; Dewey, 803 F.2d at 654. In view of the foregoing scheme, the breadth of issues covered in the contracting officerÕs decision Òdetermines the extent of the contractor's right of appeal and the board's jurisdiction.Ó Id. at 655. For example, in Dewey, we held that where the contracting officer decided only entitlement and the board thereafter decided entitlement and remanded to the parties regarding quantum, the boardÕs decision was final and thus appealable. Id. at 658.
In this case, Applied appealed two contracting officersÕ decisions to the Board. Applied I, 01-1 B.C.A. at 154,733. In the first decision, the termination contracting officer denied Applied entitlement to under-absorbed overhead costs. In the second decision, the contracting officer denied AppliedÕs claim for breach of contract. For its part, the Board only decided entitlement. Id. at 154,734. Accordingly, since the contracting officer did not decide quantum, but decided only entitlement, the BoardÕs decision on entitlement is final and appealable to this court. See Dewey, 803 F.2d at 655 (ÒIn rendering a decision as to entitlement . . . the Board decided all of the issues then before it . . . .Ó).
[5] As noted, the Board found that DLAÕs estimates were negligently prepared. The Board did not find bad faith on the part of DLA. A finding of bad faith is not a prerequisite to a claim for breach of contract based upon faulty estimates. As the Court of Claims explained in Womack, Ò[a]n inadvertent misrepresentation stemming from negligence is fully as damaging as a deliberate one to the party who relies on it to his detriment.Ó 389 F.2d at 800.
[6] The case on which the Board relied for the proposition that AppliedÕs breach damages may include anticipatory profits, Carchia, 485 F.2d 622, is inapposite. In Carchia, the government wrongfully terminated a construction contract for default. At the time, a wrongful default termination was treated as a breach of contract. As the Court of Claims stated, Ò[s]ince this was an old-style contract which did not provide that a wrongful default termination was to be considered a convenience-termination, plaintiff was entitled to anticipated profits for work not yet performed at the time it received the improper notice of default termination.Ó Id. at 625. In Carchia, the government did not dispute entitlement to anticipated profits, only the amount of such profits.
[7] The Board will have to determine whether, as asserted by the contracting officer in her final decision, the termination settlement compensated Applied for DLAÕs breach.
[8] In Cactus Press, the Board rejected the contractorÕs claim because it was untimely. In HKH Capitol Hotel Corp., the contractorÕs claim was barred because the contractor did not seek clarification of a patent ambiguity in the contract relating to the estimate. 98-1 B.C.A. ¦ 29,548 at 146,472
[9] Equally inapplicable, so far as computation of damages is concerned, are the diversion cases, when lost profits recovery is allowed because the government has improperly diverted orders to other sellers. Ante at 13-18 (discussing Ace-Federal Reporters, Inc. v. Barram, 226 F.3d 1329 (Fed. Cir. 2000); Torncello v. United States, 681 F.2d 756 (Ct. Cl. 1982); Locke v. United States, 283 F.2d 521 (Ct. Cl. 1960)).