| DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release. |


| | JC | UDS |
| Technical and Business Management Proposal (1,000 points) | 899 | 888 |
| Technology/Design | | |
| i. DUF6 Conversion (200 points) | 188 | 192 |
| ii. Waste and Conversion Product Disposition (100 points) | 83 | 84 |
| Project Management | | |
| i. Method of Accomplishment (150 points) | 141 | 134 |
| ii. Project Management Systems (100 points) | 92 | 87 |
| Business Management (150 points) | 137 | 132 |
| Environment, Safety, and Health (150 points) | 125 | 119 |
| Experience (100 points) | 98 | 94 |
| Past Performance (50 points) | 35 | 46 |
| Cost, Fee, and Revenue Evaluation (millions) | | |
| Contract Period | ||
| Total Estimated Probable Costs | $506.7 | $493.7 |
| Proposed Maximum Fee | $ 60.6 | $ 63.3 |
| Total Probable Costs and Maximum Fee | $567.3 | $557.0 |
| Probable Revenue | $ 51.0 | $ 24.7 |
| Post-Contract Period | | |
| Total Estimated Probable NPV Cost | $768.1 | $712.3 |
| Probable NPV Revenue | $114.6 | $ 75.1 |