| DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release. |


| 1. Cost to the Air Force[6] | |
| 2. Financial Strategy | |
| 3. Facility Capability | |
| | A. Building Core and Shell |
| B. Tenant Improvements | |
| C. Integration with Area B Facilities | |
| 4. Project Management | |
| | A. Project Execution Plan |
| B. Project Management Team | |
| 5. Proposal Risk | |
| 6. Past Performance | |
| | Factor | |||||
| | Cost[10] (in millions) | Financial Strategy | Facility Capability | Project Management | Past Performance | |
| SES | $29 (10 yr lease) $13 (30 yr lease) | Blue | Blue | Blue | Blue | |
| | Risk (10 yr lease) | Moderate | Low | Low | N/A | |
| | Risk (30 yr lease) | High | Low | Low | N/A | |
| | | | | | | |
| Kearny | $13 (10 yr lease) | Green | Blue | Blue | Blue | |
| | Risk | Moderate | Low | Low | N/A | |
| Costs & Funding Sources | Amounts (in millions) |
| Total Project Costs | $115.5 |
| Funding Sources-- Land Values | $54.7 |
| --Tax Increment Financing | $47.7 |
| --Brownfields Grant | $2 |
| --Total | $104.4 |
| Cost Gap (Project Costs minus Funding Sources) | $11.1 |
| AF Management Reserve | $2 |
| Gap with AF Management Reserve | $13.1 |